প্রশ্নপত্রে ফিরুন
Bank Math Master

প্রশ্ন আইডি · d6eea5fa80d7138a9145e6926458c89e

Bank Math Master
১টি পরীক্ষায় এসেছেপ্রশ্ন ৮
A contractor employs 45 persons to do a job in 40 days. After 10 days, it was found that only one-sixth of the work was finished. How many more persons are to be employed to finish the job as per schedule?