১টি পরীক্ষায় এসেছেপ্রশ্ন ৪
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for 3200 Tk. With the help of C they completed the work in 3 days. How much is to be paid to C?