A, B, and C completed a work costing Tk 2250. A worked for 6 days, B for 4 days, and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much will A receive?
সঠিক উত্তর: গ
গ) 750 Tk
উত্তর
সঠিক উত্তর: গ
গ) 750 Tk
ব্যাখ্যা
Question: A, B, and C completed a work costing Tk 2250. A worked for 6 days, B for 4 days, and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much will A receive?
Solution:
Let the daily wages of A, B, and C be Tk 5x, 6x, and 4x respectively.
Then, ratio of their amounts
=(5x × 6) : (6x × 4) : (4x × 9)
= 30 : 24 : 36
= 5 : 4 : 6
∴A's amount = 2250 × (5/15) = 750 Tk